PPP PROJECTS UNDER PRE-CONTRACT REGULATIONS AS AT JANUARY 19, 2018 | |||||
S/N | MDA | PROJECT / DESCRIPTION | SECTOR | STATUS | PHASE |
1 | Federal Ministry of Agriculture and Rural Development | 24 Silo Storage ComplexesProject Description (Solicited Proposal): This will involve the Concession of 24 grain storage (silos) complexes. | Agriculture | Negotiation with preferred bidders commenced on 31st October and ended on 14th November, 2017. | Procurement |
2 | Federal Ministry of Power, Works & Housing. | Solar Power Generation Facilities Development of Electrical Solar Power at Power House, Maitama. 750KW daytime on the rooftop. |
Energy | Financial bid opening took place on December 12, 2017 and financial bid evaluation was conducted on December 13, 2017. Three (3) firms were short listed.Final result is yet to be approved and announced. | Procurement |
3 | National Petroleum Corporation (NNPC)/ Federal Ministry of Petroleum | Trans-Nigeria Gas Pipeline: Nigerian(Solicited Proposal): The project involves the construction of 614km gas pipeline from Ajaokuta to Kano with off take Gas Stations in Abuja, Kaduna and Kano.
|
Energy | Price negotiations for the 3 Lots have been concluded and the report submitted to NNPC management. OBC Certificate of Compliance was granted by ICRC on 10th July 2017.
Negotiations in progress |
Procurement
|
4 | Federal Ministry of Power, Works & Housing (FMPWH) | Small & Medium Dams:Project Description (Solicited Proposal): This involves the development of hydroelectric power from small & medium dams across the country to generate about 45MW of off-grid power for the dam environments. The dams involved are Ikere Gorge, Bakalori, Doma, Omi-Kampe, Challawa, Tiga, Jibiya and Zobe dams.
The Commission granted eight (8) OBC Certificates of Compliance for the projects. Thereafter the Ministry presented six (6) of the certificates (excluding Challawa and Tiga dams) to the FEC in November 2016 which were approved. |
Energy | Technical and Financial bids were received on January 11th, 2018 | Procurement |
5 | Federal Ministry of Health | Warehouse in a Box Project:The WIB Project seeks to provide physical infrastructure – an insulated warehouse, made up of pre-engineered modular components (prefabricated insulated expanded polystyrene sandwiched panels) – as well as the fittings and operating components, including offices, furnishings, racking, kitting, security and office equipment (Lagos and Abuja), for refrigeration of health commodities like vaccines etc and subsequent distribution to needed locations. | Health | The Commission issued an OBC Certificate of Compliance on March 10th 2017.Facilities currently under interim management pending conclusion of PPP process.
A meeting to review RFQ was held on December 11, 2017 RFQ has been issued.
|
Procurement |
6 | Federal Ministry of Industry Trade and Investment/National Automotive Council | Development of World Class Training Centre of Excellence:(Solicited Proposal): The National Automotive Design Development Council wishes to develop a World Class Training Centre of Excellence through a PPP. | Trade and Investment | Negotiation meeting held on Tuesday, December 19th 2017, between NADDC and PAN Learning Centre, the preferre`d bidders.
Negotiations with preferred bidder ongoing
|
Procurement;
|
7 | Federal Ministry of Water Resources | Gurara 1 Multi-Purpose Dam, Kaduna State: (Solicited Proposal): This involves the Operations and Maintenance of 30MW hydroelectric power from Gurara 1 multi-purpose dam, Kaduna State. The construction has been completed, while the evacuation facilities are at advanced stage. |
Energy | OBC Compliance Certificate issued to the Ministry (October 25th, 2016)
Awaiting submission of Technical and Financial Bids (20th February 2018) |
Procurement
|
8 | Federal Capital Territory/ Abuja Infrastructure Investment Center (AIIC) | IGR Automated Platform for AEPB: Project Description (Solicited Proposal): The project proponent proposes providing an automated system for managing revenue collections, via an ePayment platform that incorporates Mobile POS devices and a powerful AEPB office revenue administration and monitoring platform. |
Urban Development | Evidence of competitive bidding process and all documentation and approvals during the process were sent by AIIC to the Commission on October 3, 2017 Next Step: The Commission is awaiting FBC submission by MDA for review. |
Procurement |
9 | Federal Ministry of Transportation / Nigeria Shippers Council (NSC)
|
The Dagbolu Inland Container Depot (ICD):(Solicited Proposal) The project concerns the development of a Greenfield ICD in Osun State, South-West Nigeria. The ICD is being developed to exploit the strategic advantages in Nigeria’s huge export and import market by making the country a trans-shipment hub for the West African region. The ICD when developed would provide storage and cargo handling facilities for export and import of containerized cargos to and from the hinterland of Nigeria especially around the Southwest states of Ondo, Ekiti, Osun; Edo State and Kwara State. | Ports | The Commission has re-issued the Nigerian Shippers’ Council (NSC) an Outline Business Case Certificate November 8th, 2017.
Awaiting FEC approval to proceed to Procurement phase |
Development |
10 | Federal Ministry of Transportation / Nigeria Shippers Council (NSC) | Development of Inland Container Depot (ICD) in Lolo, Kebbi State: (Unsolicited Proposal): The FGN, as part of the Economic Reform Programme, approved the setting up of Lolo Inland Container Depots (ICD) to provide port services to shippers.Outline Business Case (OBC) received from the Nigeria Shippers Council (NSC) in respect of the unsolicited proposal developed by Deltatlantic Nigeria Ltd. |
Ports Sector | The Commission has re-issued the Nigerian Shippers’ Council (NSC) an Outline Business Case Certificate November 8th, 2017.
Awaiting FEC approval to proceed to Procurement phase |
Development |
11 | Federal Ministry of Transportation / Nigeria Shippers Council (NSC) | Development of Inland Container Depot (ICD) in Onitsha, Anambra State: This has a design that consists of an annual 5,000 TEUs capacity facility which can be expanded with increasing throughout. | Ports Sector | The Commission has issued the Nigerian Shippers’ Council (NSC) an Outline Business Case Certificate November 8th, 2017.
Awaiting FEC approval to proceed to Procurement Phase |
Development |
12 | Federal Ministry of Transportation (FMoT)/ National Inland Waterways Authority (NIWA) | Onitsha River Port Concession(Solicited Proposal): The FGN adopted PPP arrangements to develop four river ports in the Lower Niger, namely:
i. Onitsha ii. Lokoja iii. Baro and iv. Oguta River Ports. Onitsha River Port was selected as the pilot case. The World Bank is sponsoring the project development and procurement phases for the Inland Port Concession. |
Ports Sector | An OBC Certificate of Compliance was issued to NIWA on October 31st, 2016RFP has been issued to the shortlisted firms and the Commission raised issue of non inclusion of ICRC fees in the RFP and advised that addendum should be issued to the bidders and extend the bid submission date to ensure compliance.
Awaiting FEC approval to proceed to Procurement phase |
Development |
13 | Federal Ministry of Transportation / Akwa Ibom State Government | Ibom Deep Sea Port Project(Solicited Proposal): The Ibom Deep Sea Port (IDSP) project involves the development of a Greenfield Deepsea Port and accompanying Free Trade Zone (FTZ) in Akwa Ibom State in the South-South geopolitical zone of Nigeria. The proposed Port and FTZ are part of the proposed Ibom Industrial City initiative that will be established on a 14,400 hectare site donated by the Akwa Ibom State Government (AKSG) at no value. The IDSP project is intended to become a major national and regional economic gateway that will provide additional container handling capacity for the country. In addition to containers, the IDSP is expected to handle petroleum products (export and import), crude oil and natural gas (export), vehicles (import) and bulk trade in natural resources (import and export).
It is planned to be the deepest port in the West African sub-region. |
Ports Sector | The project is currently in Procurement Phase. The Commission granted an Outline Business Case (OBC) Compliance Certificate to the project on October 8th, 2014. Thereafter, the Federal Executive Council (FEC) approved the OBC on 11th May, 2015. The Federal Ministry of Transportation and AKSG are required to proceed to the project procurement phase. PWC has been appointed as project managers
RfQ has been advertised Next Step: Commencement of the competitive bidding process to select a preferred proponent (Concessionaire). |
Procurement |
14 | Federal Ministry of Interior/Nigeria Immigration Service | Establishment of Nigerian Passport application support Centres in the US, Canada etc(Solicited Proposal) | Security | The Commission has issued an OBC Certificate of Compliance. (January 5th, 2018) | Procurement |
15 | Federal Ministry of Power, Works and Housing/Council for the Regulation of Engineering in Nigeria | COREN Head Office Project(Solicited Proposal): The proposal will involve the Construction of COREN head office complex in Abuja using PPP procurement methodology.
|
Urban Development | The Commission has granted an OBC Certificate of Compliance on 8th November 2016 for the project to enable the Council to obtain the Federal Executive Council (FEC) approval to commence the Procurement Phase where the private sector project proponent will be selected. | COREN has been advised to proceed to procurement. |
16 | Federal Ministry of Transportation (FMoT) / Nigeria Ports Authority (NPA) | Kirikiri Port Lighter Terminal I & II(Solicited Proposal): The Kirikiri area is part of Tin Can Island Port Complex (TCIPC) and is located about 1,500m away from the Western tip of Tin Can Island, along a channel connected to Badagry Creek. Over three decades the terminal infrastructures have been decaying due to lack of maintenance. In 2006 however decision was taken to revitalise the Kirikiri area and parts of the terminals (26 ha on KLT I and 16 ha on KLT II) were set apart for concession to private investors. KLT I was to be dedicated to general cargo traffic, whereas KLT II was to be dedicated to container storage. The area to be conceded included a 1,000 m long quay wall on KLT I and a 760 m long quay wall on KLT II, as well as sheds, warehouses and offices. | Ports Sector | OBC Certificate of Compliance was issued on October 28, 2016. Evaluation of Technical proposals for the concession of Kirikiri Lighter Terminal II (KLT II) was held on 5th – 6th October, 2017 at Lagos.Next step: Project to undergo financial bid opening on 12/1/2018 (kirikiri 2) |
Procurement
|
17 | National Commission for Museums & Monuments/ Federal Ministry of Information & Culture | Development of Recreational Park within the Museum premises, Enugu. (Unsolicited Proposal): An unsolicited proposal submitted to the National Commission for Museums & Monuments to develop recreational park in Enugu, within the Museum premises. |
Culture | OBC Certificate of Compliance granted on 16th October 2017. EoI has been prepared for advert.The Project being an unsolicited proposal shall go through Swiss Challenge procurement to ensure competition and TransparencyNext Step: Submission and Evaluation of EoIs. |
Development |
18 | Federal Ministry of Tourism and Culture | National Theatre (Solicited Proposal): The project involves the development of 65 hectares of the 134 hectares fallow land around the National Theatre by building 5-star hotel, office buildings, leisure Park, shopping mall and Multi Level car park. |
Culture | Full Business Case (FBC) Certificate of Compliance revalidation has been granted by ICRC.Next Step: Awaiting FBC approval by FEC | Procurement |
19 | Federal Ministry of Interior | ECOWAS Biometric ID Cards SystemThis project involves the adoption of smart card and biometric technology to secure the identification of documents as a prerequisite for managing migration and to enhance regional security, which is the outcome of the deliberation of ECOWAS Heads of Governments in order to meet the challenges posed by migration. | Security | The Ministry was issued an OBC Certificate of Compliance on the 16th of February, 2017. Next Step: Awaiting FEC approval of OBC compliance certificate |
Development |
20 | Federal Ministry of Defence | Concession of Defence Jetty, Marina Lagos
Messrs. Inspium Multi-Services Limited (IMSL) is proposing through a Build-Operate and Transfer (BOT) PPP model the rehabilitation and construction of the Ministry of Defence Jetty at Marina, Lagos. Once Complete the following services will be available: Ferry Service Parking, Helicopter Parking, Car Parking, Office Letting, Berthing Services, Afloat Repair Services, Warehousing Services, Restaurants & Café, Professional Training Services. |
Security | The Commission has issued the Federal Ministry of Defence an Outline Business Case Certificate November 8th, 2017. | Procurement |
21 | Federal Ministry of Power, Works & Housing | Lagos – Ibadan Expressway:The 127km Lagos to Ibadan Expressway is a very important highway in the country, but is presently in a gravely dilapidated state. The road “as is” is a dualized carriageway with lay byes in designated areas along the stretch of the road. The re-construction, rehabilitation and expansion of the road, as currently proposed, is divided into two separate sections; to be undertaken by different Construction Contractors. | Roads & Bridges | The Commission has granted a Full Business Case (FBC) Compliance Certificate for the Financing Arrangement (which does not cover Operations and Maintenance of the road). However, the FBC certificate confers on Motorways Asset Limited (MAL) the revenue rights during the Tolling, Operations and Maintenance (TO&M) Phase of the project.The Infrastructure Bank Plc is assisting the Federal Government in raising funding to cover the Engineering, Procurement and Construction (EPC) funding gap. | Procurement |
22 | Federal Ministry of Transportation / NPA | Port Single Window:The project involves the introduction of electronic single window platform that can effectively coordinate all port related/cargo clearance activities capable of potentially transforming port operations to a seamless, paperless system by eliminating redundant procedures and duplications. | Ports Sector | The Ministry is in the process of procuring a Transaction Adviser (TA) to prepare an Outline Business Case (OBC) to determine the project’s viability and bankability. | Development |
23 | Federal Ministry of Transportation / NPA | National Freight Intelligence and Transportation Hub (NAFITH):The project involves an application of information and communications technology (ICT) in the management of transport problems. It seeks to leverage on new innovation to provide needed solutions to the teething transport problems in Apapa. | Ports Sector | The Ministry is in the process of procuring a Transaction Adviser (TA) to prepare an Outline Business Case (OBC) to determine the project’s viability and bankability. | Development |
24 | Federal Ministry of Transportation / NPA | Koko Port Concession:FGN is seeking to grant a new Concession over the Koko Port in 2017. NPA is conducting hydrographic studies to determine the best way the channels leading to Koko port could be optimally utilized. The transaction described herein will consist of the contiguous NPA lands and NPA facilities between the river and the public roadway that runs behind the port property and including the area behind the existing quay. The transaction for this general cargo port will consist of a 180 m quay and apron, and a transit shed.
A plan view of the Koko Terminal lease will consist of the following facilities:
Not included in this transaction are the jetty and other facilities or equipment currently used by Tower Petroleum for bulk liquid (bitumen) handling.
|
Ports Sector | The Ministry is in the process of procuring a Transaction Adviser (TA) to prepare an Outline Business Case (OBC) to determine the project’s viability and bankability. | Development |
25 | Federal Ministry of Transportation / NPA) | Ikorodu Lighter Terminals:The port is dedicated to salvaging unclaimed or overtime containers in the ports, with a view to providing needed solutions to port congestions and pave way to smoothen the new concessionaire’s operations in the ports. | Ports Sector | The Ministry is in the process of procuring a Transaction Adviser (TA) to prepare an Outline Business Case (OBC) to determine the project’s viability and bankability. | Development |
26 | Federal Ministry of Transportation / NPA) | Provision of Utilities to the Ports:The FGN is desirous in using PPP procurement method for the provision of utilities to the ports. These include, but are not limited to the provisions of power and water. | Ports Sector | The Ministry is in the process of procuring a Transaction Adviser (TA) to prepare an Outline Business Case (OBC) to determine the project’s viability and bankability. | Development |
27 | Federal Ministry of Transportation (FMoT) / NPA) | Development of Deep Sea Port in Badagry, Lagos:The Badagry Port project is a Greenfield development designed to cater for containers, dry bulk, liquids, Ro-Ro, oil & gas supply services, and also operate a free trade and local logistic zones. | Ports Sector | The Commission issued an OBC Compliance Certificate on 29thDecember 2015 to enable the Ministry seek FEC approval which was granted on 3rd August, 2016. | Procurement |
28 | Federal Ministry of Transportation (FMoT) / NPA | Lagos Port IPP (of NPA) 36MW: Provision of power to Port Concessionaires | Ports Sector | A ‘No Objection’ (equivalent of FBC Compliance Certificate) has been granted to NPA for 36MW Lagos Port IPP | Procurement |
29 | Federal Ministry of Transportation (FMoT) / NPA
|
Onne Port IPP (of NPA) 144MW: Provision of power to Port Concessionaires – Phase One of 72MW | Ports Sector | A ‘No Objection’ (equivalent of FBC Compliance Certificate) has been granted to NPA for 72MW | Procurement |
30 | Federal Ministry of Transportation (FMoT)/ National Inland Waterways Authority (NIWA)
|
PPPs for the following facilities:i. Warri Dockyard
ii. Lokoja Dockyard iii. Concession of Abam Ama Jetty at Port Harcourt iv. Buoyage Vessels (B/V Anam at Onitsha) v. Buoyage Vessels (B/V Bajibo at Lokoja, Kogi State) vi. Buoyage Vessels (B/V Nembe at Lokoja, Kogi State) vii. Buoyage Vessels (B/V Numan at Lokoja, Kogi State) viii. Motor Ferry (M/F Calabar at Lokoja, Kogi State) ix. Motor Ferry (M/F Effiat Mbo at Lokoja, Kogi State) x. Motor Ferry (M/F Donga at Makurdi, Benue State) xi. Water Bus (W/B) at Yauri, Kebbi State xii. 3 Nos. 40-45 Passenger Sitter Ferries at Lokoja, Kogi State xiii. Water Hyacinth Clearing Equipment (Water Master Classic III at Onitsha) xiv. 2 Nos. 40-45 Passenger Sitter Ferries at Lagos xv. Marina Jetty at Lagos xvi. Apapa Jetty at Lagos xvii. Oyingbo Jetty at Lagos xviii. Maraoko Jetty at Lagos xix. Abayomi Drive Jetty at Lagos xx. Osborne Jetty at Lagos xxi. Calabar Jetty at Calabar |
Ports Sector | The Ministry is in the process of procuring Transaction Advisers (TAs) to prepare an Outline Business Case (OBC) to determine the projects’ viability and bankability.
|
Development |
31 | Federal Ministry of Transportation / Nigeria Shippers Council (NSC) | Development of Container Freight Depot (CFD) in Ogwashi-Uku, Delta State:This has a design that consists of an annual 5000 Twenty-foot Equivalent Units (TEUs) capacity facility which can be expanded with increasing throughput. The site measures approximately 100 hectares. | Ports Sector | The Ministry is in the process of procuring a Transaction Adviser (TA) to prepare an Outline Business Case (OBC) to determine the project viability and bankability. | Development |
32 | Federal Ministry of Transportation / Nigeria Shippers Council (NSC) | Development of Inland Container Depot (ICD) in Benin, Edo State: The Benin Dry Port is proposed to act as a port of destination for container cargoes waiting for further delivery instructions. It is also proposed to provide services for the unloading of full container loads and breaking them down into smaller lots per consignee.The primary objective of establishing the BENIN DRY PORT is to provide a one stop cargo reception and clearance facility to boost exports from and imports into Edo State particularly and Nigeria’s South-South, South East and some States in the Middle Belt regions in general. It is expected to provide proper handling and logistics services which emphasize promptness, dependability and cost effectiveness. | Ports Sector | The Ministry is in the process of procuring a Transaction Adviser (TA) to prepare an Outline Business Case (OBC) to determine the project’s viability and bankability. | Development |
33 | Federal Ministry of Transportation / Nigeria Shippers Council (NSC) | Development of Truck Transit Park (TTP) in Obollo-Afor, Enugu State:The NSC proposes to facilitate the development of TTPs through PPP with facilities for short-term breaks as well as long-term parking services where truck drivers can get fuel, food, restrooms, showers and basic supplies like oil and spare parts as well as servicing and repairs of haulage vehicles. The Truck Transit Parks will have the following facilities including but not limited Gas Station, Hotel and Motel, Restaurants, Mechanic Workshop, Fire Station, Police Post, Automated Cargo Tracking System. | Ports Sector | The Commission has issued OBC Compliance Certificate. | Procurement |
34 | Federal Ministry of Transportation / Nigeria Shippers Council (NSC) | Development of Truck Transit Park (TTP) in Lokoja, Kogi State:The NSC also proposes to facilitate the development of TTPs through PPP with facilities for short-term breaks and also long-term parking services where truck drivers can get fuel, food, restrooms, showers and basic supplies like oil and spare parts as well as servicing and repairs of haulage vehicles. The Truck Transit Parks will have the following facilities including but not limited to Gas Station, Hotel and Motel, Restaurants, Mechanic Workshop, Fire Station, Police Post, Automated Cargo Tracking System. | Ports Sector | The NSC in compliance with the guidelines of the Commission now seeks the services of a Transaction Adviser to provide a broad range of advisory services; to prepare an Outline Business Case (OBC) to determine the project’s viability and bankability.
Submission and Evaluation of RfP took place 21st June, 2017 in NSC Head Office Lagos. |
Development |
35 | Federal Ministry of Transportation / Nigeria Shippers Council (NSC) | Gombe Container Freight Station:This is a green field project aimed at providing a common user facility outside the seaport area for shipping operators, logistics firms, freight forwarders and other relevant stakeholders to ease the movement of import and export cargoes to and from the hinterland.
In support of the project, the Gombe State Government has allocated about 128 hectares of land/site for the project. |
Ports Sector | The Ministry is in the process of procuring a Transaction Adviser (TA) to prepare an Outline Business Case (OBC) to determine the project’s viability and bankability. | Development |
36 | Federal Ministry of Transportation | Development of the Bakassi Deep Sea Port:The Cross River State Government (CRSG) as part of its infrastructural development, plans to develop a deep sea port at Bakassi under PPP arrangement, in pursuance of which it sought the collaboration of the Federal Government of Nigeria in accordance with existing legal framework for port development in implementing the proposal. | Ports Sector | Transaction Adviser has been selected. | Development |
37 | Federal Ministry of Transportation /NRC) | Concession of the Narrow Gauge: Eastern Railway (Port Harcourt to Maiduguri); Western (Lagos to Kano) railway lines in the Country:The total length of the narrow gauge system is about 3,500km excluding passing loops and sidings. The Lagos to Nguru via Kaduna section with branch lines to Apapa, Idogo, Baro and Kaura Namoda (Western Line) was built between 1898 and 1915 and measures 1,800km and the Port Harcourt to Maiduguri via Kafanchan section with a connecting line from Kafanchan to Kaduna and branch lines to Eleme and Jos (Eastern Line) was built between 1914 and 1926 and the 1960 and measures 1,700km. The two lines are interconnected by a link between Kafanchan and Kaduna. | Rail | African Finance Corporation (AFC) Consortium was appointed as TA by the Ministry to support the Concession exercise. OBC Compliance Certificate was issued to FMoT on April 7th, 2017, subject to meeting some conditions at the FBC level.FMoT are negotiating with the GE Consortium on Concession agreement.A meeting was held on 6th October 2017 at FMoT. |
Procurement |
38 | Federal Ministry of Transportation /NRC | Development of Greenfield Railway Lines:i. Lagos – Shagamu- Ijebu Ode- Ore- Benin City (300km) (standard gauge)
ii. Benin- Agbor-Ogwashi Uku- Asaba- Onitsha –Nnewi- Owerri-Aba with additional line from Onitsha-Enugu- Abakaliki (500km) (standard guage). iii. Ajaokuta(Eganyi)-Obajana-Jakura-Baro-Abuja with additional line from Ajaokuta- Oturkpo(533km) (standard guage). iv. Zaria- Funtua- Tsafe- Gusau- Kaura- Namoda-Sokoto-Illela-Birnin Koni (520Km) (standard guage). v. Lagos -Ibadan- Oshogbo-Baro-Abuja (615KM) (high speed). |
Rail | The Ministry is in the process of procuring a Transaction Adviser (TA) to prepare an Outline Business Case (OBC) to determine the projects viability and bankability. | Development |
39 | Federal Ministry of Transportation / (NIMASA)
|
i. Ship building yard with breaking, recycling technology and wreck identification and removal.ii. Management and operations of the modular/floating dry dock (outsourcing).
iii. Procurement of operational vessels, maritime patrol aircraft, coordination/surveillance centre and other operational equipment (Finance lease) iv. Outsourcing of NIMASA’s Training Centre and Guest House at Nigerian Maritime Resource Development Centre (NMRDC), Kirikiri, Lagos state. v. PPPs to develop a Multilevel car park at NIMASA Headquarters vi. Unsolicited proposal for Development of platform for pollution vii. Verification Gross Mass Imo Solar- safety of life at sea |
Maritime
|
The Ministry is in the process of procuring a Transaction Advisers (TAs) to prepare an Outline Business Case (OBC) to determine the projects viability and bankability | Development |
40 | Federal Ministry of Transportation | Concession of 4 International Airports (Abuja, Lagos, Kano and Port Harcourt):The Federal Government of Nigeria (FGN) will concession the Abuja, Lagos, Port Harcourt and Kano international airports in the first phase of its concession programme. The government was committed to upgrading the existing facilities at the airports as well as developing new strategy to reposition the sector, just like every other place in the world, FGN will concession the airports and are beginning with the big four. | Aviation | TA has been procured. | Development |
41 | Federal Ministry of Transportation | i. Establishment of a Maintenance, Repair and Overhaul (MRO) Centerii. Development of Aerotropolis (Airport City)
iii. Development of Cargo/Agro-Allied Airport Terminals iv. Establishment of a National Carrier v. Setting up of Aviation Leasing Company |
Aviation | TA has been procured. | Development |
42 | Federal Ministry of Trade & Investment / Tafawa Balewa Square Management Board (TBSMB) | Rehabilitation, Management and Operation of the National Trade and International Business Centre, Lagos (NTIBC):The development of the NTIBC was conceived against the background of the FGN’s desire to develop one-stop investment hubs in order to sustain economic growth by encouraging export, enterprise and investments. The Independence building was built in 1959. The building consists of 25 floors, has approximately 8,100 square meters and a separate parking lot directly opposite with an area of 2,650 square meters.
The proposed NTIBC building will be a mixed-use facility to cater for businesses on a let basis, provide space for TBSMB and also residential usage. The proposed facility will be multi-functional, to include: i. Office for agencies under the FMITI ii. Offices for other government MDAs iii. Information hub on trade & investment in Nigeria iv. Office for Blue-Chip companies v. Conference & meeting rooms vi. Exhibition and banquet halls vii. Restaurants & lounge bar |
Trade & Investment | Transaction Adviser has been procured and prepared an Outline Business Case (OBC). OBC Certificate of Compliance was issued by ICRC on November 14, 2016 to enable the Ministry obtain FEC approval for the proposal. | Development |
43 | Federal Ministry of Trade & Investment / National Automotive Council (NAC) | Establishment of the Mechanic’s Villages:The mechanics’ villages’ project is an initiative of NAC, a body established pursuant to the National Automotive Council Act, Cap N8, Laws of the Federation of Nigeria, with responsibility for the development of the automotive industry in Nigeria.
The objective for the establishment of the mechanic’s villages is, among other things, to stimulate the growth and development of the mechanic business in a specialized and orderly manner. The project is aimed at developing the automotive value chain via the provision of 6 pilot modern mechanic villages in the nation’s 6 geopolitical zones. |
Trade & Investment | Transaction Adviser has been procured and has prepared an Outline Business Case (OBC). | Development |
44 | Federal Ministry of Trade & Investment / Small and Medium Enterprises Development Agency of Nigeria (SMEDAN) | Development of 23 Industrial Development Clusters (IDCs):The objective of the project is to redevelop 23 Industrial Development Centers (IDCs) into Industrial Clusters across Nigeria (in 6 geopolitical zones) using the PPP Model. | Trade & Investment | Logic Triangle has been selected as TA for preparation of OBCs. Site visit to the 23 IDCs Centers was conducted and led by the TA, Logic Triangle in December, to be concluded in January. |
Development |
45 | Federal Ministry of Industry Trade and Investment | Federal Ministry of Industry Trade and Investment Abuja Head office Building Project:The Federal Ministry of Industry Trade and Investment is desirous to build their Abuja Head Office through a PPP Procurement method. Project Conceptualization is currently on-going. | Trade & Investment | Project Conceptualization is currently on-going.
|
Development |
46 | Federal Ministry of Water Resources | Gurara 2 Greenfield Multi-Purpose Dam:The Concession of the Gurara 2 Greenfield multi-purpose Dam, Niger State includes 300MW of hydropower components of the dam.
|
Energy | The project is currently in Development Phase. The project land is encumbered and the Ministry is resolving the issue. Thereafter, the Outline Business Case is expected to be forwarded to ICRC.
ICRC has written to the Ministry seeking updates on the project. Awaiting the Ministry’s response. |
Development |
47 | Federal Ministry of Water Resources | Owena Multi-Purpose Dam water supply – Unsolicited Proposal:The project will provide about 1.5kwh of electricity to the national grid. | Energy | The Outline Business Case of the project has been reviewed and ICRC has granted OBC Certificate of Compliance on 10th march 2017. The Ministry is expected to present the OBC certificate to FEC for approval. | Development |
48 | Federal Ministry of Water Resources | Development of 9MW Oyan Dam Unsolicited:This involves the Operations and Maintenance of 9MW hydroelectric power. | Energy | OBC Certificate of Compliance has been granted.The Ministry is expected to present the certificate to FEC for approval. | Development |
49 | Federal Ministry of Water Resources | Development of 420MW River Mada Medium hydropower plant in Nasarawa State:This involves the Operations and Maintenance of 420MW hydroelectric power.
|
Energy | The OBC review for Mada River hydropower generation project has been concluded. Observations on the OBC have been sent to the Ministry for necessary action. | Development |
50 | Federal Ministry of Water Resources | Other PPP Projects:i. Development of Tede Dam for Hydro power and other purposes.
ii. Concession of Oturkpo Dam for Hydro Power and other purposes. iii. Development of Dasin Hausa Dam for Hydro power and other purposes. |
Energy | The Ministry is in the process of procuring Transaction Advisers (TAs) to prepare Outline Business Cases (OBC) to determine the projects’ viability and bankability. | Development |
51 | Federal Ministry of Mines and Steel | Ajaokuta Steel company Ltd & National Iron Ore Mining Company (NIOMCO):Rehabilitation, completion, management and operation of Ajaokuta Steel Company and National Iron Ore Mining Company (NIOMCO) through PPP Concession agreement.
|
Energy | A meeting held with His Excellency the Ag. President and all parties have agreed that GINL would submit draft “Terms for a commercial arrangement” for use of the central rail lines with due respect to the 2014 Settlement Agreement. The Attorney General’s Office will come up with a draft concession agreement on behalf of MMSD (FGN) for consideration by both parties.Both Parties have also agreed to consider a commercial agreement with NRC through FMOT for the use of the central lines for freight of goods by GINL. The Ministry is making efforts to ensure that the ASCL is released to the Federal Government by Global Infrastructure Nigeria Limited |
Procurement/ Implementati-on |
52 | Federal Ministry of Agriculture and Rural Development | Other Projects, involving PPPs on:i. Federal Coastal Fishery Terminal, Ebughu, Akwa Ibom State
ii. Fish Processing Centre, Jebba, Kwara State iii. Agro Aviation Hangar, Kaduna |
Agriculture | The Ministry is in the process of procuring Transaction Advisers (TAs) to prepare Outline Business Cases (OBC) to determine the projects’ viability and bankability
|
Development |
53 | Federal Ministry of Interior / Nigerian Prison Service | Concession of Nigerian Prisons Land Swap Correctional Facility, Industrial Laundry Facility & Integrated Farm Facility | Security | First phase of Negotiation with preferred bidders for both Land Swap Correctional Facility (Halcrow Infrastructure Consortium) and Integrated Farm Facility (Nestoti Consortium) projects took place on the 28th of June 2016 | Development |
54 | Federal Ministry of Interior / Nigerian Prisons Service | The proposal is for the Rehabilitation, Expansion and Operation of the Nigerian Prisons Service Shoe Factory (NPS SF) Aba, Abia State under Public Private Partnership between Erojim Investment limited (EIL) and the Nigeria prisons service. | Security | Outline Business Case Compliance Certificate was issued on 30th December, 2016.The Commission has advised NPS to commence procurement process which will lead to the preparation of a Full Business Case (FBC) and the emergence of a preferred project proponent and forward along with the OBC to the Commission for revalidation and issuance of a Joint OBC/FBC Compliance Certificate to enable NPS seek Federal Executive Council (FEC) approval. | Procurement |
55 | Federal Ministry of Interior
|
The Ministry also seeks to use PPP procurement methodology to develop the following projects:i. Passengers Information System
ii. Information Verification System iii. Security Guards Biometric Data Collection, Verification and Authentic System iv. Construction of an ultra modern forensic laboratory at the Police Headquarters Building in Abuja. v. Renovation and refurbishment of the Obalende & Falomo Police Barracks in Lagos. |
Security | The Ministry is in the process of procuring Transaction Advisers (TAs) to prepare Outline Business Cases (OBC) to determine the projects viability and bankability. | Development |
56 | Defence Industries Corporation of Nigeria (DICON) | PPP projects involving:i. Establishment of selected weapons and military equipment assembly lines
ii. Establishment of Mobile Solar Powered Generating set iii. Production of Ballistic Vests and Procurement of Raw Material |
Security | The Ministry is in the process of procuring Transaction Advisers (TAs) to prepare Outline Business Cases (OBC) to determine the projects’ viability and bankability. | Development |
57 | Federal Ministry of Interior (Defence) | Supply, Operate & Maintain arrangement for equipment to MoD, for leasing to the UN under CoE system on a letter of assist basis:This arrangement will give the Nigerian Armed Forces access to high-grade military equipment to carry out their duties. | Security | The Commission has granted an OBC certificate of compliance on 7th July 2015 for this project. | Development |
58 | Federal Ministry of Interior (Police Affairs) | Supply Own and Operate( SOO) of Contingent Owned Equipment to Peace Keeping Missions in CAR, South Sudan, Somalia, Dafur and Liberia:This arrangement will give the Nigerian Armed Forces access to high-grade military equipment to carry out their duties. | Security | Certificate of Compliance issued in 2016 for the review of the OBC/FBC has expired but will be re-validated after a second review on the Financial Model. | Procurement |
59 | Federal Ministry of Defence | The Naval Ship Dockyard:This involves the development of Naval Dockyard around the country through PPP Procurement process. | Security | The Commission has reviewed the OBC and issued an Outline Business Case Compliance Certificate on 10th July 2017 | Development |
60 | Federal Ministry of Health / University of Port Harcourt Teaching Hospital (UPTH) | Construction of staff housing estate, shopping complex and new House Officers’ (Doctors’) quarters | Health | The PDT met on 24th October and 1st November to review the Draft Full Business Case prepared by the Consultants | Procurement |
61 | Federal Ministry of Health | Abuja Medical Mall/City:This involves the development of a tertiary medical facility (Medical Mall/City) on a greenfield site in Abuja to harness the potential of the private health sector and provide high quality alternatives to Nigerians who require specialist medical care in the country. | Health
|
The Ministry is in the process of procuring a Transaction Adviser (TA) to prepare an Outline Business Case (OBC) to determine the project viability and bankability. | Development |
62 | Federal Ministry of Health | Development of Oncology Centre of Excellence for Cancer Care in 8 Teaching Hospitals across the Geopolitical zones Federal Ministry of Health:The FGN through the Federal Ministry of Health seeks to procure and manage Oncology equipments in Federal Teaching Hospitals across the Country. | Health | The PDT has adopted the option of Traditional Procurement/Leasing where payment is tied to equipment management and service/the continuous function of the machine on service delivery.
Awaiting further steps from the Ministry |
Development
|
63 | Federal Ministry of Health | Upgrade of the 3rd Phase of Teaching Hospital Rehabilitation ProjectThe contracts for rehabilitation and modernization of select Federal Teaching Hospitals (8 in phase 1 and 6 in phase 2) were awarded in November 2002 and September 2006 respectively to VAMED Engineering Ltd and a Presidential Project Implementation Committee was set up to monitor proper and timely execution of the projects.
The remaining 7 Teaching hospitals were supposed to be rehabilitated and modernized through PPP and a Technical Working Group (TWG) with membership drawn from FMOH, NSIA, ICRC, and four members from private sector was set up to deliberate and agree with VAMED/CPL Group on the most suitable PPP model to be adopted for phase 3. |
Health | Inaugural meeting was held on the 25th of August, 2017 at the Minister’s Conference RoomThe Company was asked to incorporate all observations raised and re-submit.
Facilicomm Nig. Ltd have been appointed as TA to the project. The Commission wrote the Ministry requesting to meet with the TA. |
Development |
64 | Federal Ministry of Health | Orthopedic Hospital, Dala- Kano The proposed PPP seeks to construct staff quarters within the premises, conversion of existing bungalow within the hospital premises to commercial guest house, equipping of the Hospital mortuary building and Equipping, Furnishing and Operation of a Private wing of the Hospital. | Health | The Ministry is in the process of procuring a Transaction Adviser (TA) to prepare an Outline Business Case (OBC) to determine the project viability and bankability. | Development |
65 | Federal Ministry of Communication Technology / NIPOST | CBN- NIPOST Financial Inclusion: Increase of Financial Inclusion (FI) penetration rate in the country by providing banking services to the financially excluded population through NIPOST offices nationwide. | ICT | PDT meeting held on 12thOctober, 2017 and proposed three (3) PPP ModelsPSC to decide the preferred Model of PPP to be adopted | Development |
66 | Federal Capital Development Authority (FCDA) | Automated Parking Centres:This involves the construction of Automated Parking Centres in designated car parks in the FCT. | Urban Development | FCDA is in the process of procuring a Transaction Adviser (TA) to prepare an Outline Business Case (OBC) to determine the project viability and bankability. | Development |
67 | Federal Housing Authority (FHA) | PPPs involving the following:i. Development of new towns in Abuja at Kwali and Bwari Area Councils
ii. PPP to develop corporate head office of Federal Housing Authority (FHA) in Abuja located at the Central Business District of Abuja. |
Urban Development | FHA is in the process of procuring Transaction Advisers (TAs) to prepare an Outline Business Cases (OBC). | Development |
68 | Federal Ministry of Power, Works & Housing (Housing) | Marina Quayside Strip Project:The proposed project is a transformative urban/waterfront development Project intended to be a tourism centre that will provide Hotels, Condominiums, Commercial Complexes, Water Sports, Restaurants, Art Galleries, Cinemas, Shops, Car Parks, Bus Transport Terminals, Museums, Offices, Residential buildings, Rented Houses, Theme parks, Parks, Port Authorities, Cruise Ship Facilities, Jetties, Boardwalks, Marinas, Aquaria, Sports Complexes, Casinos, Medical Facilities and Marine Transport. | Urban Development | The updated Outline Business Case (OBC) has been reviewed by ICRC and certificate of compliance awarded August 16, 2017 | Development |
69 | Federal Ministry of Power, Works & Housing (Housing) | New Eko Development Project, (Lagoon City) in Lagos:The project proposal involves the Sand-filling and reclamation of water bodies within the vicinity of existing Banana Island Estate. The project would redefine the Banana Island landscape and complement the development of Lagos lagoon to reflect its mega-city status. | Urban Development | The OBC is currently a work in progress by the FMoPW&H. | Development |
70 | Federal Ministry of Youth and Sports | PPPs involving the following:i. Upgrading/rebuilding of National Stadium, Lagos
ii. Completion of Athletes’ hostel, Abuja
|
Sports | Ministry has written to BPP for restrictive tendering for the services of TA.TAs submitted their Technical & Financial bids to the Ministry. They are yet to be harvested. Awaiting further action from the Ministry. | Development |
71 | Office of the Head of Civil Service of the Federation (OHCSF) | Federal Civil Service Staff ClubThe Office of the Head of Civil Service of the Federation (OHCSF) wishes to embark on a brownfield PPP project for the Operations & Maintenance of the abandoned Federal Civil Service club at Mabushi, Abuja. | Urban Development | The Project is currently in the Development stage. The Ministry is required to engage a Transaction Adviser (TA) to prepare a Business Case (OBC) to determine the project bankability. | Development |
72 | Federal Ministry of Education | PPPs involving the following:i. Upgrade of the ICT Laboratories/Business Centers in Federal Schools
ii. Upgrade of existing libraries iii. Upgrade of vocational schools |
Education | The Ministry is in the process of procuring Transaction Advisers (TAs) to prepare Outline Business Cases (OBC) to determine the projects’ viability and bankability. | Development |
73 | Federal Ministry of Education | National Mathematical Center:i. Development of an International Conference Center
ii. Construction of National Mathematical Centre-International Science Academy (NMC-IMSA) |
Education | The Ministry is in the process of procuring Transaction Advisers (TAs) to prepare Outline Business Cases (OBC) to determine the projects’ viability and bankability. | Development |
74 | Federal Ministry of Education / Federal University Gusau (FUG) | PPPs involving the following:i. Proposed construction of Students Hostel, 500-Units of Staff Housing, Roads & Drainages, Shopping Mall, Staff/Students Cafeteria, Bio-gas Electricity Power plant and Poultry Farm
ii. On-line application System for e-registration platform, Computation / compilation of Students’ results, e-Learning and web portal development. iii. Proposed construction of Vice Chancellor’s Lodge, Pro-Chancellor’s Lodge, Principal Officers’ Quarters, Senior Staff Housing, Junior Staff Housing, External Electrification, Borehole & Overhead Tanks, etc |
Education | The Ministry is in the process of procuring Transaction Advisers (TAs) to prepare an Outline Business Cases (OBC) to determine the projects’ viability and bankability
ICRC reviewed the submitted documents in line with our processes. University written to supply additional information on the project and also confirm availability of land space for the entire project. |
Development |
75 | Federal Ministry of Education | Computer Based Test Centre (National Business And Technical Examinations Board):The Computer Based Test (CBT) Centre project is to enhance efficiencies of candidates in Technical and Vocational Education through Information and Computer Technology.
|
Education | The Project is currently functional but the NABTEB has been asked by the Commission to forward relevant documents on the project to the Commission.The Business Case and Executed Contract Agreement were reviewed and it was found that it did not satisfy the key features of PPP contracts. The Commission requested additional documents to incorporate the issues raised.
The Board has been advised to submit a Joint OBC/FBC for review. |
Procurement |
76 | Ministry of Information and Culture | Development of National Council for Arts and Culture’s land through PPP: The Council is desirous of developing an edifice on its parcel of Land located at Central Business District, Abuja through PPP that will comprise the following:i. Culture and Arts Theatre
ii. Office Development for use by NCAC iii. Conference and event exhibition hall; and iv. Shopping Mall |
Culture | The Ministry is required to engage a Transaction Adviser (TA) to prepare an Outline Business Case (OBC) to determine the project viability and bankability. | Development |
77 | Federal Ministry of Education
|
Development of commercial hub at National Open University of Nigeria (NOUN): The National Open University of Nigeria is desirous of building a commercial hub for the University Community within the campus at Jabi, Abuja using the PPP arrangement. The complex will have the following facilities Banking malls, Supermarket, Restaurants, Bookstore, retail shops etc | Education
|
Issued an OBC Certificate of Compliance on the 7th October, 2017 | Development |
78 | Federal Ministry of Environment (FMoE) | PPPs on the following:i. Establishment of Federal Ministry of Environment’s Clean and Green Campaign to end open defecation in public areas by 2019 by providing Public Toilets nationwide. Pilots to be in FCT public schools, motor parks and market places; and extended to the 36 States.
ii. Framework for Plastic Industry and other private sector companies to take plastic waste off the streets by 2019 iii. Development of a New Head Office for the Federal Ministry of Environment (to be completed in 2018) |
Environment | The Ministry is in the process of procuring Transaction Advisers (TAs) to prepare Outline Business Cases (OBC) to determine the projects’ viability and bankability. | Development |
79 | Federal Ministry of Industry, Trade and Investment | Development of Okerete Transnational Border Market at Saki West LGA, Oyo StateThe Federal Ministry of Industry, Trade and Investment wants to establish transnational border markets to promote regional integration, create employment in rural areas and reduce high incidence of smuggling across Nigeria’s borders. The intention is to create them at 6 geo-political zones of the country starting with Okerete, in South West region. | Industry, Trade and Investment | The Ministry is in the process of procuring a Transaction Adviser to prepare an Outline Business Case to determine the project viability and bankability.It was unanimously agreed at the Technical Committee meeting that the road leading to the site should be graded and tarred as well as constructing a bridge that will link Nigeria and Republic of Benin.
Ministry have been advised to engage the services of a TA. |
Development |
80 | Federal Ministry of Education/ University of Abuja | Development of Students Hostel at University of Abuja The University of Abuja is desirous to build hostels for its teeming students as well as staff housing estate through PPP procurement methodology. |
Education | Project development is currently ongoing. | Development |
81 | Public Private Partnership for upgrade and concession of hostel at Public Service Institute of Nigeria | Upgrade and Concession of Properties through PPP methodology Public Service Institute of Nigeria is desirous of using PPP procurement methodology to upgrade and concession to private party its 108 rooms female hostel and another 27 rooms purpose built guest chalet. |
Education | The project is currently in development phase. The Institute is working with consultants to prepare an Outline Business Case (OBC) to determine project viability and bankability.
|
Development |
82 | Federal Ministry of Health (FMoH) | Establishment of Anti-Snake Venom Production Facility in Nigeria through PPP.Federal Government (FG) of Nigeria through the Federal Ministry of Health seeks the Establishment of Anti-Snake Venom Production Facility through PPP. On the strength of the above, a meeting was called by the Ministry to discuss the project on the 20th of June, 2017 | Health | The Ministry is in the process of procuring a Transaction Adviser to prepare an Outline Business Case to determine the project viability and bankability.
Meeting held on two occasions on the way forward. Ministry to give further directive. |
Development |
83 | Federal Ministry of Power, Works & Housing. | Transformer Repair Services The project is an unsolicited proposal submitted by Kilowatt Electrics Limited (KWEL) to the Nigerian Electricity Management Services Agency (NEMSA). KWEL is proposing a joint venture partnership with NEMSA to operate the transformer repairs workshop in Ijora Lagos and construction of transformer repair workshops in Port Harcourt and Kaduna centers. The partnership will also include the role of electrical inspection, testing and certification of all electrical installation hitherto performed by NEMSA. |
Energy | OBC Compliance Certificate granted 16th August 2017
A work plan for the project was circulated by ICRC at the PDT meeting that took place on 21st November, 2017 Preparation of draft Expression of Interest (EOI) is ongoing.
|
Development |
84 | Federal Capital Territory/ Abuja Infrastructure Investment Center (AIIC) | Small Hydropower Embedded Power from the Wupa Water Treatment Plant Effluent Discharge. Wupa Water Treatment Plant Project on a Build Operate and Transfer (BOT) PPP model to produce electric power from the effluent discharge from the plant.Power generation capacity is estimated at 3,346.29kW/day which would power the WWTP and also provide the input for the production of fertilizer and plastics.The power plant is expected to sell excess power to the national grid. |
Energy | Draft OBC sent by MDA and reviewed by the Commission August 8, 2017Meeting held with project stakeholders on August 16, 2017 | Development |
85 | Federal Ministry of Power, Works & Housing. | Concession of 1.2MW Grid Connected PV Solar Power Plant Concession of 1.2MW Grid Connected PV Solar Power Plant at Lower Usuma Dam, Abuja under the Japanese Grant-In-Aid to the FGN |
Energy | OBC Certificate of Compliance was issued on 13th September, 2017. | Development |
86 | Development of Shopping Mall, University College Hospital (UCH), Ibadan. Federal Ministry of Health/UCH, Ibadan |
Development of Shopping Mall, University College Hospital (UCH), IbadanUCH seeks to develop a Shopping Mall through PPP Procurement | Education | Sensitization workshop and Inaugural PDT meeting held between the 17th – 19th of October, 2017 at the Hospital premises | Development |
87 | Federal Ministry of Environment | Establishment of a bamboo value chain Establishment of a Bamboo Value Chain Business including maintaining, managing and scaling up the Bamboo factory in Lokoja, Kogi state under PPP |
Environment | Ministry to update OBC and send back to the Commission by 3rd January 2018. | Development |
88 | Federal Ministry of Petroleum Resources | NNPC Refineries Rehabilitation ProjectThe project will involve the rehabilitation of refineries across the country. | Energy | Inter-Ministerial Steering Committee Meeting on Rehabilitation of Nigeria’s Refineries took place on the 17th October, 2017 | Development |
89 | Federal Ministry of Health\ Federal College of Education (Technical) Bichi, Kano State. | Development of hostel facilities and supermarketFCE Bichi (Technical) seeks guidance to develop hostel accommodation. |
Health | The submitted document has been reviewed and the College has been asked to submit additional documents.The Commission is awaiting FCE Bichi response. | Development |
90 | Federal University, Wukari/Federal Ministry of Education | Development of hostel facilities and accommodation for Staff and Students | Education | The submitted document has been reviewed and the University was advised to prepare an OBC for the projectAwaiting Federal University Wukari response | Development |
91 | University of Calabar Teaching Hospital. Federal Ministry of Health | Unsolicited proposal for the Design, Build, Manage and Transfer of Students & Staff residential accommodation within the Hospital premises on PPP arrangement (Proposed by PETROBARA). | Health | Review of Document in Progress | Development |
92 | ONEX through Mpape-Gurku-Ado/Gurku-Nyanya in the Federal Capital Territory (FCT), Abuja. FCTA | The project involves the construction, operation and maintenance of Dual Carriage way from Outer Northern Express Way (Murtala Mohammed Way) through Mpape to Gurku, through Ado/Gurku. The project was designed to ease congestion on Nyanya road and its surrounding axis. | Road | The project is at development phase involving procurement of Transaction Adviser and preparation of Outline Business Case (OBC). | Development |
93 | Mabushi District Engineering Infrastructure Development, Abuja. FCTA | The project provision of engineering infrastructure in Mabushi District. Mabushi District is a 460 hectares land area located within Phase II of the Federal Capital Territory. The scope of work includes Site Clearance and Earthworks, Surface Water Drainage, Road Works, Bridge Works, Culverts, Street lighting, Wastewater Drainage, Power Supply and Conduits, Conduits for Post and Telecommunications, Water Distribution Network. | Urban Development | The Project is stalled | Stalled |
94 | Federal Capital Territory | Light Rail Lot 2 PPP ProjectThe proposed Abuja Light Rail PPP project includes the financing, designing, construction, operation and maintenance of the rail transit network route. The covering distance is 54.1 kilometers from Garki Area 11 passing through the interchange centre at Eagle Square to Gudu and down to Nyanya, Karu axis, in Abuja. It also connects to sector Centre D through Hilton Hotel, Gwarimpa FHA Estate and the light railway Lot 1 (Blue line currently under construction) | Urban Development | A meeting was held on December 22, 2017 at the SGF’s office whereby IRMG made another presentation on the way forward with the project. Although no conclusive agreements were reached, due to absence of some stakeholders and the meeting was adjourned to a later date.Date of meeting to be communicated to the Commission. | Development |
95 | Federal Ministry of Petroleum Resources | Construction Of LPG And Ethanol/Methanol Plants At Emede Uzere Delta State (On Public Private Partnership (PPP) Basis)
The construction of an LPG and Ethanol/Methanol Plant at Emede Uzere, Delta State from Everlinksourcing Ltd to the Ministry of Petroleum Resources. |
Energy | The Commission wrote a letter to Federal Ministry of Petroleum 22nd of December, 2017 requesting an update on the process so far and inviting the Ministry for a meeting.Meeting scheduled for Tuesday 16, January, 2018. | Procurement |